Project News

Major Construction and Move Planning Milestones Achieved

The Archives and Special Collections Building project continued to progress steadily during September through November, advancing from nearly 60% complete to an estimated 67% completion, with major milestones achieved both inside and outside the facility.

Key accomplishments included execution of a contract with movers to begin planning for the eventual relocation of collections, installation of nearly all interior walls and door frames, significant progress on vault infrastructure in preparation for shelving installation, release of the furniture package for bidding, and substantial advancement of exterior features including ramps, planters, curtain walls, and loading dock construction. By November, the building was increasingly reflecting its final design, with upper-level spaces beginning to take their finished shape and infrastructure work continuing to support the transition to the next phase of construction.

Archives and Special Collections Building Construction Passes Midpoint

Renovation work on the Archives and Special Collections Building continues to make steady progress. As of July 23, 2026, the project was approximately 53% complete and has passed the halfway point in its overall schedule.

Construction crews are making progress both inside and outside the building. Brickwork is continuing around the southeast plaza, and new walls are being prepared and built in several areas. Interior work is also moving forward, including installation of upper-level walls, insulation, and other building systems such as plumbing, electrical, heating, and cooling.

Additional milestones include preparation of the loading dock and generator area, installation of ductwork, completion of electrical work for the west entrance ramp, and installation of elevator door frames. Crews have also poured the concrete base for the west ramp, applied protective coatings to the plaza deck, installed equipment in the south mechanical room, and completed masonry work around the generator enclosure.

Throughout the building, work continues to prepare spaces for the next phases of construction as the renovation moves steadily toward completion.

In preparation for taking possession of the space in mid-2027, the university recently concluded a search for a qualified firm to assist with moving the collections into the facility. The first on-site planning meeting with the firm is being scheduled for this coming September.

Construction at 35% Completion and Opening Date Announced

Construction is progressing steadily on the new Archives and Special Collections Building, with the project now about one-third complete. Crews are continuing waterproofing work around the plaza and courtyard areas, including installing protective walkways to keep those surfaces intact. Inside the building, walls and door frames are being built on the upper level, while major systems such as plumbing, electrical, and heating and cooling are being installed throughout.

Work is also advancing on key structural features. This includes installing ductwork, continuing below-ground plumbing on the lower level, and adding conduit for electrical systems. Crews have begun work on the roof over the west pavilion, are making progress on a new elevator, and have partially installed new stairways. Additional work includes masonry walls, equipment foundations, and ongoing site cleanup and grading.

The building is expected to be completed in July 2027. Following construction, the Library will coordinate the move of the Rare Book & Manuscript Library, University Archives, and Illinois History and Lincoln Collections, along with their staff and collections, into the new space. A grand opening is planned for Spring 2028.

Experience the build as it happens—check out live construction of the new Archives and Special Collections Building through the Morrow Plots Cam on the University of Illinois Urbana-Champaign’s YouTube channel.

Below are photos taken on March 26, 2026, highlighting the developments on site.

Campaign to Transform the University Library
Email: webmaster@library.illinois.edu