Proposed Project Schedule

The kick-off meeting included a review of the proposed project schedule from the point that “conceptualization” began on July 21, 2021, through what is called “substantial completion” of construction work. Those dates in the future become increasingly speculative. At present, the schedule is as follows:

  1. Conceptualization
    07/21/2021 work session
    08/12/2021 submission date
  2. Schematic Design
    11/09/2021 submission date
  3. Design Development
    01/22/2022 submission date
  4. Construction Documents 50%
    03/31/2022 submission date
  5. Construction Documents 95%
    07/04/2022 submission date
  6. Bidding/Award
    08/18/2022 Advertise for Bids
  7. Board of Trustees approval (required on if individual contract is over $2,500,000.)
  8. Construction – Start/End *
    01/05/2023 – 05/29/2024